Glenrowen Homes - letter 12/07/2023
Dear residents,
We write to inform you that we have some planned dates for road works on Main Road and Quarry Lane, Leadenham to enable site works. During this time there will be traffic lights in place to manage traffic as well as some road closures.
Planned road works dates:
Opposite the garage, Main Road, Leadenham – Two way traffic light management - 7th August – 22nd with a road closure to the A607 on the weekend of 12th – 14th August.
Main Road and Quarry Lane, Leadenham – 23rd August – 15th September where there will be traffic lights as well as:
Road closure to the A607 on the weekend of 26th – 28th August
Road closure to Quarry Lane 26th August – 15th September
All necessary traffic management has been agreed and will be in place. All businesses will be open as usual. Some bus services and stops may be suspended from Leadenham to Wellingore 12th – 14th August & 23rd – 25th August.
We apologise for any inconvenience caused in advance and hope to complete this works as swiftly as possible.
Kind regards
Daniel Selby
Daniel Selby MCIOB
Project Manger
Glenrowan Homes
m.07500 838975